  • 20 TONS LIFTING CAPACITIED, DOUBLE SPEEDED and 19.3 m SPAN PORTAL CRANE:
    All calculations are done and design and manufacturing projects are prepared.
    [ Divriği Pellet Plant - Kutlutaş ]
  • SLIDE GATE 900x900 HAND AND ELECTRICAL DRIVEN
    Projecting, calculating, manufacturing, trying.
  • REFULATING VALVE (radius 900) hand and electrical driven.
  • TRASHRACKS, BULKHEAD GATES AND PENSTOCK.
    Projecting, calculating, manufacturing of trashrack and Bulkhead Gates.
    [ Güldürcek Dam/DSİ - Suta ]
  • BULK CEMENT TRANSPORT TANK.
    Pnomatic filing up, pouring out systems.
  • DRINKING AND IRRIGATINGWATER DISTRIBUTING NETWORK
    Calculations, design and detailed manufacturing project.
    [ DSİ - Gaziantep ]
  • SLIDING MOULD PROJECT
    Calculations, design and detailed manufacturing project.
    [ Urfa Tunnel ]
  • HANDLING SYSTEM OF MATERIAL DETERGENT CONVEYORS, ELEVATORS, SCREW CONVEYORS PNOMATICLY OPERATED BUTTERFLY GATES ELECTRONIC BATCHING WEIGHER.
    [Turyag - İzmir ]
  • CARBON BLACK STORAGE, FEEDING DAILY TANKS, PREPARATION of C/9 for BUNBURY MIXERS,
    Complete design and detailed manufacturing projects, manufacturing erectioning and taking into operation.
    Contract includes also eletronic control system and electronic batching weighers.